Find out if you need consent
Here you’ll find descriptions along with cross section diagrams of the types of work that:
- require consent
- do not require consent
- require consent in some cases
If you’re planning multiple works, you’ll need to apply for consent for each one separately. This applies to both permanent and temporary works.
Temporary works include cofferdams (watertight enclosures) across a watercourse, or temporary diversions of water. Permanent works could be the installation of a bridge.
If you’re not sure whether the type of work you’re planning requires consent, you can contact us for advice.
What happens if you carry out works without consent
We may take legal enforcement action (not necessarily criminal sanction) against you if you carry out damaging or potentially damaging works without consent, or if you breach any consent we’ve granted.
We’ll also charge you for any work we have to do to repair the damage.
If you suspect someone has carried out works to a watercourse without proper consent, then you can report it in confidence to us.
Works that require consent
If you’re planning any of the following types of work, you need to apply for consent under Section 23 of the Land Drainage Act 1991.
Bridge where soffit level is below bank top level

Requires consent under Section 23 (1)(b) as it acts like a culvert.
Bridge with abutments restricting flow

Requires consent under Section 23 (1)(b) as it acts like a culvert.
Diversion of a watercourse, temporary or permanent

Requires consent under Section 23 (1)(a).
Oversized box culvert

Requires consent under Section 23 (1)(b). This includes extending or removing an oversized box culvert.
Pipe crossing (in channel)

Requires consent under:
- Section 23 (1)(a) if placed on a bed
- Section 23 (1)(b) if placed above bed
Pipe culvert

Requires consent under Section 23 (1)(b). This includes extending or removing a pipe culvert.
Trash screen

Requires consent under Section 23 (1)(c), as it’s an alteration to a culvert and may obstruct flow.
Weir, dam, impoundment or temporary works that obstruct flow

Requires consent under Section 23 (1)(a).
Works that do not require consent
The following types of work do not require consent under the Land Drainage Act 1991.
Bank protection works

Does not require consent. However, you may need consent for temporary bank protection works.
Bridge with abutments not reducing flow area or width

Does not require consent as it does not interfere with flow.
Bridge with support in channel

Does not require consent as it does not act like a dam, weir or any similar obstruction.
Clear span bridge

Does not require consent as it does not interfere with flow.
Outfall within bank profile

Does not require consent as it does not act like a mill dam or weir.
Pipe crossing above bank

Does not require consent as it does not affect the watercourse.
Pipe crossing below bed

Does not require consent as it does not interfere with flow. However, you may need consent for temporary works that include a pipe crossing below the bed.
Protruding pipe outfall

Does not require consent as it does not act like a dam, weir or any similar obstruction.
Works that require consent in some cases
If you’re planning any of the following types of works and you’re not sure if you need consent, you can contact us for advice.
Temporary bank protection works
Some temporary bank protection works may require consent.
We would discourage the use of a pier in the watercourse. For any pier, you should consider its size against the size of the watercourse.
Temporary pipe crossing below bed
You may need consent for temporary works that include a pipe crossing below the bed.
About this information
The information on this page is based on the Environment Agency’s interpretation of legislation. ‘Flow’ should be determined as bank full flow conditions.