September 2026 update
Work continues to progress well on the Marple Hub development, with a number of key milestones achieved over the past month as the project moves closer to completion.
Latest progress
Significant progress has been made across the site, including:
- demolition of the former clinic building has now been completed
- new air source heat pumps have been installed within the plant room, supporting the hub's energy-efficient and sustainable design
- screeding works around the perimeter of the swimming pool have been completed
- construction of the swale drainage feature is progressing, with fencing installed and reduced-level excavation works underway
Looking ahead
Over the next 4 weeks, the project team will be focusing on:
- continuing construction of the swale drainage system
- starting formation of the new car park
- beginning both hard and soft landscaping works across the site
- starting internal decoration works within the building