January 2026 update

Works have been progressing on Marple Hub over the last couple of months:

  • the roof is being installed along with the insulation and top grey sheets
  • metal framing to the external wall has started to the west side of the building
  • construction of the ground floor slabs has begun in the cafĂ© and community space
  • the pool base concrete slab has been poured

Looking ahead, works that will take place include:

  • continuing with roofing, including insulation to the central section and top sheets
  • external wall metal framing and weather boarding on the west and south elevations
  • completing the ground floor slabs to the changing village
  • completing the pool tank walls and forming the pool surround
  • beginning the internal blockwork to the plant areas and changing village

Marple Clinic will be moving to Brabyns Brow (Upper) Middlers car park in January 2026.

The hub will open in autumn 2026.

Below, you can view images of the progress so far.

Marple Hub aerial view January 2026

An aerial view of Marple Hub under construction and the surrounding area.

Marple Hub exterior January 2026

Marple Hub in progress.

Marple Hub frame structure January 2026

Works inside the construction of Marple Hub.