Infrastructure Funding Statement 2022 to 2023
Financial report summary for 2022 to 2023
The following information provides an overview of the expenditure that took place during the 2022 to 2023 financial year:
- £3,332,018.50 was agreed
- £1,724,657.38 was received
- £986,973.48 was spent
- £10,714,416.40 was retained
Find more information about these categories on the previous page.
Section 106 (Planning Obligations) Statement 2022 to 2023
We're required to publish specific information relating to section 106 contributions in accordance with Regulation 121A, Schedule 2, Section 2 of the Community Infrastructure Levy Regulations (2019 amendment).
The following information sets out these requirements and the corresponding amounts for the 2022 to 2023 monitoring year.
Requirement 3(a)
This is the total amount of money to be provided under any planning obligations which were entered into during the reported year.
| Infrastructure type | Amount |
|---|---|
| Affordable housing | £612,118.00 |
| Open space | £2,179,176.50 |
| Transport | £457,500.00 |
| Monitoring fee with uplift | £68,550.00 |
| Biodiversity Net Gain | £14,674.00 |
| Total | £3,332,018.50 |
Requirement 3(b)
This is the total amount of money under any planning obligations which was received during the reported year.
| Infrastructure type | Amount |
|---|---|
| Affordable housing | £1,247,261.00 |
| Open space | £342,673.22 |
| Transport | £86,302.32 |
| Monitoring fee | £39,631.84 |
| Biodiversity Net Gain | £8,789.00 |
| Total | £1,724,657.38 |
Requirement 3(c)
This is the total amount of money under any planning obligations which was received before the reported year which has not been allocated by the authority.
| Infrastructure type | Amount |
|---|---|
| Affordable housing | £1,700,146.00 |
| Open space | ££1,303,485.31 |
| Transport | £284,119.94 |
| Monitoring fee | £45,489.75 |
| Biodiversity Net Gain | £0.00 |
| Total | £3,333,741.00 |
Requirement 3(d)
This includes summary details of any non-monetary contributions to be provided under planning obligations which were entered into during the reported year, including:
- (i) in relation to affordable housing, the total number of units which will be provided
- (ii) in relation to educational facilities, the number of school places for pupils which will be provided, and the category of school at which they will be provided
| Requirement | Infrastructure type | Amount |
|---|---|---|
| (i) | Total | 83 |
| (ii) | Total | 210 school places (Woodford Primary School) |
Requirement 3(e)
The total amount of money (received under any planning obligations) which was allocated but not spent during the reported year for funding infrastructure was £5,877,799.16.
Requirement 3(f)
The total amount of money (received under any planning obligations) which was spent by the authority (including transferring it to another person to spend) was £986,973.48.
Requirement 3(g)
This is in relation to the money (received under planning obligations) which was allocated by the authority but not spent during the reported year. This includes summary details of the items of infrastructure on which the money has been allocated and the amount of money allocated to each item.
| Infrastructure type | Amount |
|---|---|
| Affordable housing | £695,593.00 |
| Open space | £4,146,810.50 |
| Transport | £1,035,395.66 |
| Biodiversity Net Gain | £0.00 |
| Monitoring fee | £0.00 |
Requirement 3(h)
This is in relation to money (received under planning obligations) which was spent by the authority during the reported year (including transferring it to another person to spend). This includes summary details of:
- (i) the items of infrastructure on which that money (received under planning obligations) was spent, and the amount spent on each item
- (ii) the amount of money (received under planning obligations) spent on repaying money borrowed, including any interest, with details of the items of infrastructure which that money was used to provide (wholly or in part)
- (iii) the amount of money (received under planning obligations) spent in respect of monitoring (including reporting under regulation 121A) in relation to the delivery of planning obligations
| Requirement | Infrastructure type | Amount |
|---|---|---|
| (i) | Affordable housing | £171,000.00 |
| Open space | £534,804.00 | |
| Transport | £281,169.48 | |
| Biodiversity Net Gain | £0.00 | |
| (ii) | n/a | |
| (iii) | Monitoring | £0.00 |
Requirement 3(i)
This is the total amount of money (received under any planning obligations) during any year which was retained at the end of the reported year. This also applies where any of the retained money has been allocated for the purposes of longer term maintenance (“commuted sums”). Where appropriate, the total amount of commuted sums held is identified separately.
| Infrastructure type | Amount |
|---|---|
| Affordable housing | £3,643,000.00 |
| Open space (children's play) | £663,588.17 |
| Open space (formal sport) | £1,432,682.06 |
| Open space (children's play and formal sport maintenance) | £3,483,222.33 |
| Transport | £1,398,013.25 |
| Biodiversity Net Gain | £8,789.00 |
| Monitoring | £85,621.59 |
| Total | £10,714,416.40 |